nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #115

In which Management product would the Project Board specify where the authority for change requests lies?

The correct answer is D. Configuration Management Strategy. See the full explanation below for the reasoning.

Question

In which Management product would the Project Board specify where the authority for change requests lies?

Options

  • ARisk Management Strategy
  • BQuaky Management Strategy
  • CCommunication Strategy
  • DConfiguration Management Strategy

How the community answered

(20 responses)
  • A
    10% (2)
  • C
    5% (1)
  • D
    85% (17)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice