PRINCE2-FOUNDATION · Question #1059

How often should the 'controlling a stage' process be used during a project?

The correct answer is B. For each delivery stage in the project. See the full explanation below for the reasoning.

Question

How often should the 'controlling a stage' process be used during a project?

Options

  • AOnce, for the whole project
  • BFor each delivery stage in the project
  • CWhenever the project board meets
  • DTwice, for initiation and for the rest of the project

How the community answered

(54 responses)
  • A
    4% (2)
  • B
    74% (40)
  • C
    7% (4)
  • D
    15% (8)