How often should the 'controlling a stage' process be used during a project?
The correct answer is B. For each delivery stage in the project. See the full explanation below for the reasoning.
Question
How often should the 'controlling a stage' process be used during a project?
Options
- AOnce, for the whole project
- BFor each delivery stage in the project
- CWhenever the project board meets
- DTwice, for initiation and for the rest of the project
How the community answered
(54 responses)- A4% (2)
- B74% (40)
- C7% (4)
- D15% (8)