PRINCE2-FOUNDATION · Question #1058

How should the "managing a stage boundary' process be used towards the end of a project's final delivery stage?

The correct answer is A. To plan the activities of the closing a project' process. See the full explanation below for the reasoning.

Question

How should the "managing a stage boundary' process be used towards the end of a project's final delivery stage?

Options

  • ATo plan the activities of the closing a project' process
  • BTo implement any exception plan requests from the project board
  • CTo create a benefits management approach for corporate, programme management or the
  • DTo review an issue received from a team manager

How the community answered

(23 responses)
  • A
    83% (19)
  • C
    4% (1)
  • D
    13% (3)

Community Discussion

No community discussion yet for this question.