PRINCE2-FOUNDATION · Question #1029

PRINCE2-FOUNDATION Question #1029: Real Exam Question with Answer & Explanation

The correct answer is A. By agreeing requirements for how project work should be undertaken. See the full explanation below for the reasoning.

Question

How does the `managing product delivery' process achieve its purpose?

Options

  • ABy agreeing requirements for how project work should be undertaken
  • BBy producing highlight reports to enable the project board to oversee the work
  • CBy requiring the project manager to produce and monitor team plans
  • DBy escalating issues and risks that cannot be resolved within stage tolerance