PRINCE2-FOUNDATION · Question #1029
PRINCE2-FOUNDATION Question #1029: Real Exam Question with Answer & Explanation
The correct answer is A. By agreeing requirements for how project work should be undertaken. See the full explanation below for the reasoning.
Question
How does the `managing product delivery' process achieve its purpose?
Options
- ABy agreeing requirements for how project work should be undertaken
- BBy producing highlight reports to enable the project board to oversee the work
- CBy requiring the project manager to produce and monitor team plans
- DBy escalating issues and risks that cannot be resolved within stage tolerance