The correct answer is A. It promotes consistency of project work and the ability to reuse project assets.. See the full explanation below for the reasoning.
Question
Which is a benefit of using PRINCE2?
Options
- AIt promotes consistency of project work and the ability to reuse project assets.
- BIt includes techniques for critical path analysis and earned value analysis
- CIt enables a project manager to be accountable for the success of a project
- DIt prevents any changes once the scope of a project has been agreed