PRINCE2-FOUNDATION · Question #1010

What is documented in the project plan to support the 'manage by exception' principle?

The correct answer is A. The project's tolerances for cost and time. See the full explanation below for the reasoning.

Question

What is documented in the project plan to support the 'manage by exception' principle?

Options

  • AThe project's tolerances for cost and time
  • BA project product's quality criteria
  • CThe expected project benefits
  • DActivities to mitigate project risks

How the community answered

(45 responses)
  • A
    82% (37)
  • B
    11% (5)
  • C
    4% (2)
  • D
    2% (1)