PRINCE2-FOUNDATION · Question #1010

PRINCE2-FOUNDATION Question #1010: Real Exam Question with Answer & Explanation

The correct answer is A. The project's tolerances for cost and time. See the full explanation below for the reasoning.

Question

What is documented in the project plan to support the 'manage by exception' principle?

Options

  • AThe project's tolerances for cost and time
  • BA project product's quality criteria
  • CThe expected project benefits
  • DActivities to mitigate project risks