The correct answer is C. delivery stage. See the full explanation below for the reasoning.
Question
Identify the missing word(s) in the following sentence. The 'controlling a stage' process is used to manage and control each [ ? ] of a project.
Options
- Adelivery step
- Bbenefit
- Cdelivery stage
- Dteam plan