PRINCE2-FOUNDATION · Question #1009

PRINCE2-FOUNDATION Question #1009: Real Exam Question with Answer & Explanation

The correct answer is C. delivery stage. See the full explanation below for the reasoning.

Question

Identify the missing word(s) in the following sentence. The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

Options

  • Adelivery step
  • Bbenefit
  • Cdelivery stage
  • Dteam plan