PRINCE2-AGILE-FOUNDATION · Question #90

Which practice supports identification and assessment of uncertainties?

The correct answer is A. Risk. In Agile Foundation guidance, the risk practice is explicitly responsible for the identification, assessment, and management of uncertainties, making option A the correct answer. Risk is defined as uncertainty that, if it occurs, will have a positive or negative impact on…

PRINCE2 Practices in an Agile Context

Question

Which practice supports identification and assessment of uncertainties?

Options

  • ARisk
  • BPlans
  • CQuality
  • DBusiness case

How the community answered

(21 responses)
  • A
    86% (18)
  • B
    5% (1)
  • D
    10% (2)

Explanation

In Agile Foundation guidance, the risk practice is explicitly responsible for the identification, assessment, and management of uncertainties, making option A the correct answer. Risk is defined as uncertainty that, if it occurs, will have a positive or negative impact on objectives. Agile recognizes that uncertainty is inherent in complex and adaptive work, so effective risk management is essential to successful delivery. The risk practice focuses on proactively identifying uncertainties early, assessing their likelihood and impact, and determining appropriate responses. Agile Foundation documents emphasize that risk management in Agile is continuous rather than a one-time activity. Risks are regularly reviewed, updated, and addressed throughout the lifecycle as new information emerges. This aligns with Agile principles of transparency, inspection, and adaptation, allowing teams to respond to uncertainty in a timely and informed manner.

Topics

#risk practice#uncertainty management#PRINCE2 practices

Community Discussion

No community discussion yet for this question.