PRINCE2-AGILE-FOUNDATION · Question #92
What should be included in the project management team structure?
The correct answer is D. A description of how products are to be produced. Agile Foundation guidance, aligned with PRINCE2 and PRINCE2 Agile, explains that the project management team structure defines how the project will be managed and delivered, including clarity around roles, responsibilities, and ways of working. A key element that should be…
Question
What should be included in the project management team structure?
Options
- AThe procurement and contract needs
- BA full and firm foundation for the initiation of the project
- CThe arrangements for co-location of remote teams
- DA description of how products are to be produced
How the community answered
(37 responses)- A3% (1)
- B3% (1)
- C5% (2)
- D89% (33)
Explanation
Agile Foundation guidance, aligned with PRINCE2 and PRINCE2 Agile, explains that the project management team structure defines how the project will be managed and delivered, including clarity around roles, responsibilities, and ways of working. A key element that should be included within this structure is a description of how products are to be produced, making option D the The project management team structure is not just a list of roles; it provides context on how delivery will operate in practice. This includes how teams are organized, how responsibilities are allocated, and how products will move from concept to completion. Describing how products are to be produced ensures there is shared understanding of the delivery approach, whether it is Agile, iterative, hybrid, or otherwise. This clarity supports coordination, accountability, and effective governance throughout the project lifecycle.