Which of the following is used to support the "progress" practice?

The correct answer is B. Burn charts. In Agile Foundation guidance, the progress practice focuses on understanding, monitoring, and communicating how work is advancing toward agreed objectives and outcomes. Burn charts are a key tool used to support this practice, making option B the correct answer. Burn charts…

PRINCE2 Practices in an Agile Context

Question

Which of the following is used to support the "progress" practice?

Options

  • AAgilometer
  • BBurn charts
  • CTrading/swapping
  • DTeam skills matrix

How the community answered

(31 responses)
  • B
    94% (29)
  • C
    3% (1)
  • D
    3% (1)

Explanation

In Agile Foundation guidance, the progress practice focuses on understanding, monitoring, and communicating how work is advancing toward agreed objectives and outcomes. Burn charts are a key tool used to support this practice, making option B the correct answer. Burn charts provide a simple, visual representation of progress over time, enabling teams and stakeholders to see how much work has been completed and how much remains. Burn charts, including burn-down and burn-up charts, are widely used in Agile environments to support transparency and informed decision-making. A burn-down chart shows the remaining work decreasing over time, while a burn-up chart displays completed work against the total scope. Both formats help teams assess whether they are on track to meet their goals within a given timebox or delivery stage. Agile Foundation materials emphasize that progress should be measured based on delivered value and completed work, not on effort spent or activities

Topics

#burn charts#progress practice#monitoring

Community Discussion