PRINCE2-AGILE-FOUNDATION · Question #89
In which process is a workshop conducted to agree the Definition of Ready (DoR) and Definition of Done (DoD)?
The correct answer is A. Initiating a project. Agile Foundation guidance, aligned with PRINCE2 Agile, explains that the Definition of Ready (DoR) and Definition of Done (DoD) should be agreed as early as possible to establish clear expectations around quality, readiness, and completion. The workshop to agree both DoR and…
Question
In which process is a workshop conducted to agree the Definition of Ready (DoR) and Definition of Done (DoD)?
Options
- AInitiating a project
- BDirecting a project
- CControlling a stage
- DManaging product delivery
How the community answered
(56 responses)- A95% (53)
- B2% (1)
- D4% (2)
Explanation
Agile Foundation guidance, aligned with PRINCE2 Agile, explains that the Definition of Ready (DoR) and Definition of Done (DoD) should be agreed as early as possible to establish clear expectations around quality, readiness, and completion. The workshop to agree both DoR and DoD is conducted during the Initiating a Project process, making option A the correct answer. The Initiating a Project process is where the foundations for successful delivery are set. Its purpose is to ensure that there is a shared understanding of how the project will be delivered, governed, and controlled before significant work begins. Agreeing the DoR and DoD at this stage provides clarity on what "ready to start" and "done" actually mean for the project. This helps align stakeholders, delivery teams, and governance roles on quality expectations and acceptance