PRINCE2-AGILE-FOUNDATION · Question #132

Which statement describes how the PRINCE2 'starting up a project' process can be applied in an agile environment?

The correct answer is B. PRINCE2 is predictive and can be emergent. You've hit your limit · resets 5am (America/New_York)

PRINCE2 Processes in an Agile Context

Question

Which statement describes how the PRINCE2 ‘starting up a project' process can be applied in an agile environment?

Options

  • APRINCE2 is predictive, but not emergent
  • BPRINCE2 is predictive and can be emergent
  • CPRINCE2 requires a lengthy start to a project
  • DPRINCE2 requires a disruptive start to a project

How the community answered

(18 responses)
  • B
    94% (17)
  • C
    6% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#starting up a project#emergent planning#predictive#PRINCE2 processes