PRINCE2-AGILE-FOUNDATION · Question #131
What is typically displayed on a board to show progress to people working on a project?
The correct answer is C. Information radiator. You've hit your limit · resets 5am (America/New_York)
Agile Techniques and Ceremonies
Question
What is typically displayed on a board to show progress to people working on a project?
Options
- AAgilometer assessment
- BProduct backlog
- CInformation radiator
- DUser story
How the community answered
(23 responses)- A4% (1)
- B4% (1)
- C91% (21)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#information radiator#Kanban board#transparency#progress tracking