PRINCE2-AGILE-FOUNDATION · Question #138
Which workshop extracts actionable insights for future iterations?
The correct answer is C. Project retrospective workshop. Agile Foundation guidance clearly states that the project retrospective workshop is the workshop designed to extract actionable insights for future iterations, making option C the correct answer. Retrospectives are a core Agile practice focused on learning, reflection, and…
Question
Which workshop extracts actionable insights for future iterations?
Options
- AProgress review workshop
- BProject initiation workshop
- CProject retrospective workshop
- DTeam planning workshop
How the community answered
(31 responses)- A3% (1)
- B3% (1)
- C87% (27)
- D6% (2)
Explanation
Agile Foundation guidance clearly states that the project retrospective workshop is the workshop designed to extract actionable insights for future iterations, making option C the correct answer. Retrospectives are a core Agile practice focused on learning, reflection, and continuous improvement. Their primary purpose is to help teams and stakeholders understand what has happened, why it happened, and how future ways of working can be improved. During a project retrospective workshop, participants reflect on recent iterations or delivery stages, examining aspects such as collaboration, communication, processes, tools, quality, and decision- making. The emphasis is not on assigning blame, but on identifying patterns, root causes, and opportunities for improvement. From this reflection, the team agrees on concrete, actionable actions that can be implemented in upcoming iterations to enhance effectiveness and