PRINCE2-AGILE-FOUNDATION · Question #140
For which process is the agreement on the requirements for delivery of specialist products necessary?
The correct answer is D. Managing product delivery. Agile Foundation guidance, aligned with PRINCE2 and PRINCE2 Agile, explains that the managing product delivery process is where agreement on the requirements for the delivery of specialist products is necessary, making option D the correct answer. This process focuses on the…
Question
For which process is the agreement on the requirements for delivery of specialist products necessary?
Options
- AInitiating a project
- BStarting up a project
- CControlling a stage
- DManaging product delivery
How the community answered
(61 responses)- A3% (2)
- C2% (1)
- D95% (58)
Explanation
Agile Foundation guidance, aligned with PRINCE2 and PRINCE2 Agile, explains that the managing product delivery process is where agreement on the requirements for the delivery of specialist products is necessary, making option D the correct answer. This process focuses on the interface between project management and the delivery teams, ensuring that work is clearly understood, authorized, executed, and accepted. Managing product delivery is concerned with agreeing what specialist products are to be produced, the quality expectations they must meet, and how and when they will be delivered. This agreement typically takes the form of work packages or similar delivery agreements. These clarify requirements, acceptance criteria, constraints, and reporting expectations so that delivery teams can work with confidence and autonomy. Agile Foundation documents emphasize that clarity at this point is essential to avoid misunderstandings, rework, and delays.
Topics
Community Discussion
No community discussion yet for this question.