PRINCE2-AGILE-FOUNDATION · Question #142
Which of the following is a prioritized list of the requirements for a product?
The correct answer is D. Backlog. In PRINCE2 Agile, a Backlog is the prioritized list of requirements, features, or user stories that define what needs to be delivered for a product. It is a dynamic and evolving list that is continually refined and re-prioritized to ensure the most valuable work is done first…
Question
Which of the following is a prioritized list of the requirements for a product?
Options
- AProject canvas
- BRelease map
- CProject log
- DBacklog
How the community answered
(21 responses)- B5% (1)
- D95% (20)
Explanation
In PRINCE2 Agile, a Backlog is the prioritized list of requirements, features, or user stories that define what needs to be delivered for a product. It is a dynamic and evolving list that is continually refined and re-prioritized to ensure the most valuable work is done first. The backlog acts as a single source of truth for what the team needs to deliver and provides transparency to stakeholders regarding progress and priorities. It aligns with agile principles and practices such as Scrum, where the Product Backlog contains all desired work for the product. The Project Canvas is a high-level tool used for defining project scope and objectives, the Release Map plans releases and iterations, and the Project Log tracks issues, risks, and actions but does not list prioritized requirements.
Topics
Community Discussion
No community discussion yet for this question.