In Scrum, what answers the question `what can be done this sprint?'

The correct answer is A. Daily scrum. You've hit your limit · resets 5am (America/New_York)

Agile Concepts and Frameworks

Question

In Scrum, what answers the question `what can be done this sprint?'

Options

  • ADaily scrum
  • BSprint review
  • CSprint planning
  • DIncrement

How the community answered

(35 responses)
  • A
    80% (28)
  • B
    3% (1)
  • C
    6% (2)
  • D
    11% (4)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#Scrum events#sprint planning#daily scrum#Scrum framework