Which is used to enable all involved in work to 'pull' information about targets, progress, issues, and risks?
The correct answer is C. Information radiator. You've hit your limit · resets 5am (America/New_York)
Agile Concepts and Frameworks
Question
Which is used to enable all involved in work to 'pull' information about targets, progress, issues, and risks?
Options
- ABurn chart
- BKanban board
- CInformation radiator
- DScrum artifact
How the community answered
(53 responses)- A2% (1)
- B6% (3)
- C91% (48)
- D2% (1)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#information radiator#transparency#Kanban#pull information