Which of the following uses a flow-based approach to control work in progress?
The correct answer is C. Kanban. Kanban uses a flow-based approach to visualize and control work in progress (WIP). It emphasizes limiting WIP to improve flow and reduce bottlenecks, with continuous monitoring via Kanban boards. This approach supports flexibility, transparency, and efficiency in managing
Agile Concepts and Frameworks
Question
Which of the following uses a flow-based approach to control work in progress?
Options
- AAgilometer
- BLean
- CKanban
- DScrum
How the community answered
(33 responses)- A6% (2)
- B3% (1)
- C91% (30)
Explanation
Kanban uses a flow-based approach to visualize and control work in progress (WIP). It emphasizes limiting WIP to improve flow and reduce bottlenecks, with continuous monitoring via Kanban boards. This approach supports flexibility, transparency, and efficiency in managing
Topics
#Kanban#flow-based approach#work in progress#agile frameworks