Which of the following is used to monitor progress?

The correct answer is D. Burn-down chart. The burn-down chart is a visual tool used in agile to monitor progress by tracking the remaining work against time. It provides teams and stakeholders with a clear, real-time view of project status and forecast completion, allowing for early identification of potential delays…

Agile Concepts and Frameworks

Question

Which of the following is used to monitor progress?

Options

  • ADelegation matrix
  • BSwarming
  • CT-shirt sizing
  • DBurn-down chart

How the community answered

(22 responses)
  • B
    5% (1)
  • C
    5% (1)
  • D
    91% (20)

Explanation

The burn-down chart is a visual tool used in agile to monitor progress by tracking the remaining work against time. It provides teams and stakeholders with a clear, real-time view of project status and forecast completion, allowing for early identification of potential delays or bottlenecks.