Which of the following is used to monitor progress?
The correct answer is D. Burn-down chart. The burn-down chart is a visual tool used in agile to monitor progress by tracking the remaining work against time. It provides teams and stakeholders with a clear, real-time view of project status and forecast completion, allowing for early identification of potential delays…
Agile Concepts and Frameworks
Question
Which of the following is used to monitor progress?
Options
- ADelegation matrix
- BSwarming
- CT-shirt sizing
- DBurn-down chart
How the community answered
(22 responses)- B5% (1)
- C5% (1)
- D91% (20)
Explanation
The burn-down chart is a visual tool used in agile to monitor progress by tracking the remaining work against time. It provides teams and stakeholders with a clear, real-time view of project status and forecast completion, allowing for early identification of potential delays or bottlenecks.
Topics
#burn-down chart#progress monitoring#agile metrics#tracking