In which workshop does planning for the next stage occur?
The correct answer is B. Release planning workshop. The Release Planning Workshop is the forum where planning for the next stage occurs in PRINCE2 Agile. This workshop brings together the project management team and delivery teams to plan the scope, schedule, and resources for the upcoming release or stage. It helps align…
Question
In which workshop does planning for the next stage occur?
Options
- ATeam planning workshop
- BRelease planning workshop
- CTeam retrospective workshop
- DProgress review workshop
How the community answered
(57 responses)- A2% (1)
- B93% (53)
- C4% (2)
- D2% (1)
Explanation
The Release Planning Workshop is the forum where planning for the next stage occurs in PRINCE2 Agile. This workshop brings together the project management team and delivery teams to plan the scope, schedule, and resources for the upcoming release or stage. It helps align business priorities with delivery capacity and supports incremental and iterative delivery The Team Planning Workshop focuses on more detailed planning at the team level within the release, the Team Retrospective Workshop is dedicated to reflecting on performance and improving processes, and the Progress Review Workshop is for reviewing progress against the plan rather than planning future work.