PRINCE2-AGILE-FOUNDATION · Question #152
What is a purpose of the 'project closure' workshop?
The correct answer is C. Update the project documentation. The project closure workshop is held to formally close the project, during which project documentation is updated to reflect the final state of the project, lessons learned are captured, and approvals are obtained. This ensures that all activities are completed, the project has…
Question
What is a purpose of the 'project closure' workshop?
Options
- AAlign teams with project vision
- BCreate benefits management approach
- CUpdate the project documentation
- DRefine the release map for the next stage
How the community answered
(30 responses)- A3% (1)
- C93% (28)
- D3% (1)
Explanation
The project closure workshop is held to formally close the project, during which project documentation is updated to reflect the final state of the project, lessons learned are captured, and approvals are obtained. This ensures that all activities are completed, the project has delivered its intended products, and knowledge is retained for future projects or organizational
Topics
Community Discussion
No community discussion yet for this question.