Please refer to section 10.3.2.1 in the PRINCE2 Manual. (Exception Plans are only produced if requested by the Project Board. Team Plans and the use of seperate people as Team Managers are optional…

The correct answer is B. Use of management stages. See the full explanation below for the reasoning.

Question

Please refer to section 10.3.2.1 in the PRINCE2 Manual. (Exception Plans are only produced if requested by the Project Board. Team Plans and the use of seperate people as Team Managers are optional in PRINCE2)

Options

  • AUse of Team Managers
  • BUse of management stages
  • CUse of Exception Plans
  • DUse of Team Plans

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    83% (20)
  • C
    4% (1)
  • D
    8% (2)

Community Discussion

No community discussion yet for this question.