What provision in Planning can be made for implementing Requests for Change?
The correct answer is B. A Change Budget. See the full explanation below for the reasoning.
Question
What provision in Planning can be made for implementing Requests for Change?
Options
- AProject and Stage Tolerances
- BA Change Budget
- CContingency Plans
- DAdding a contingency margin to estimates
How the community answered
(43 responses)- A14% (6)
- B74% (32)
- C5% (2)
- D7% (3)