Which of the following PRINCE2 elements are described as being the aspects of project management that must be addressed continually and in parallel throughout the project?

The correct answer is C. The Themes. See the full explanation below for the reasoning.

Question

Which of the following PRINCE2 elements are described as being the aspects of project management that must be addressed continually and in parallel throughout the project?

Options

  • AThe Principles
  • BThe Processes
  • CThe Themes
  • DTailoring PRINCE2 to the project environment

How the community answered

(44 responses)
  • A
    5% (2)
  • B
    9% (4)
  • C
    84% (37)
  • D
    2% (1)