PR2F · Question #159

Which option is NOT part of the Project Initiation Document?

The correct answer is A. Project Mandate. See the full explanation below for the reasoning.

Question

Which option is NOT part of the Project Initiation Document?

Options

  • AProject Mandate
  • BInitial Business Case
  • CProject Quality Plan
  • DCommunication Plan

How the community answered

(25 responses)
  • A
    80% (20)
  • B
    4% (1)
  • C
    12% (3)
  • D
    4% (1)