EXIN
PR2F · Question #58
The Project Board have overall control at what level?
The correct answer is C. Project level within project tolerance. See the full explanation below for the reasoning.
Question
The Project Board have overall control at what level?
Options
- ADay-to-day control for a management stage within stage tolerance
- BWork Package level within Work Package tolerance
- CProject level within project tolerance
- DAll levels of plans and tolerances
How the community answered
(18 responses)- A6% (1)
- B6% (1)
- C72% (13)
- D17% (3)
Community Discussion
No community discussion yet for this question.