EXIN
PR2F · Question #56
The Project Board needs to assess project viability at certain points as defined in the Project Plan. How does the Progress theme assist this?
The correct answer is B. Authorizing one stage at a time. See the full explanation below for the reasoning.
Question
The Project Board needs to assess project viability at certain points as defined in the Project Plan. How does the Progress theme assist this?
Options
- ASending regular Checkpoint Reports
- BAuthorizing one stage at a time
- CCreating Exception Reports when tolerances are threatened
- DReports during project closure
How the community answered
(65 responses)- A3% (2)
- B74% (48)
- C14% (9)
- D9% (6)
Community Discussion