Which is NOT an objective of PRINCE2 stages?

The correct answer is B. Identify the necessary Work Packages. See the full explanation below for the reasoning.

Question

Which is NOT an objective of PRINCE2 stages?

Options

  • AProvide an opportunity to assess the project viability
  • BIdentify the necessary Work Packages
  • CAllow clarification of the impact of an external influence
  • DEnsure that key decisions are made prior to work needed to implement them