Which of the following is FALSE regarding PRINCE2 principles?

The correct answer is A. A project should have a customer/supplier environment. See the full explanation below for the reasoning.

Question

Which of the following is FALSE regarding PRINCE2 principles?

Options

  • AA project should have a customer/supplier environment
  • BA project should manage by exception
  • CA project should focus on products
  • DA project should be tailored to suit the project environment

How the community answered

(35 responses)
  • A
    74% (26)
  • B
    14% (5)
  • C
    9% (3)
  • D
    3% (1)