EXIN
PR2F · Question #491
According to PRINCE2, which of the following are the 6 aspects of project performance to be managed?
The correct answer is D. Time, cost, scope, quality, benefits, risk. See the full explanation below for the reasoning.
Question
According to PRINCE2, which of the following are the 6 aspects of project performance to be managed?
Options
- AProcesses, themes, principles, tailoring, tolerance, roles
- BTime, cost, people, quality, progress, risk
- CTime, cost, quality, scope, tolerance, benefits
- DTime, cost, scope, quality, benefits, risk
How the community answered
(33 responses)- A6% (2)
- B15% (5)
- C6% (2)
- D73% (24)