What characteristic relates to a project having a defined start and defined end?

The correct answer is C. Temporary in nature. See the full explanation below for the reasoning.

Question

What characteristic relates to a project having a defined start and defined end?

Options

  • AUniqueness
  • BUncertainty
  • CTemporary in nature
  • DIntroduces change

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    12% (3)
  • C
    81% (21)
  • D
    4% (1)