PR2F · Question #486
There should be at least two management stages in a PRINCE2 project. Which of the following options describes those stages?
The correct answer is A. Initiation as the first stage, the remainder of the project as the second stage. See the full explanation below for the reasoning.
Question
There should be at least two management stages in a PRINCE2 project. Which of the following options describes those stages?
Options
- AInitiation as the first stage, the remainder of the project as the second stage
- BInitiation as the first stage, closure activities as the second stage
- CProcurement as the first stage, design and implementation as the second stage
- DPre-project work as the first stage, initiation as the second stage
How the community answered
(20 responses)- A75% (15)
- B5% (1)
- C5% (1)
- D15% (3)