PR2F · Question #487
Please refer to section 1.3 and 'Programme' in the Glossary of the PRINCE2 Manual. (Note that a collection of related projects being directed to deliver outcomes and benefits related to the…
The correct answer is B. A temporary organization that is created for the purpose of delivering one or more business. See the full explanation below for the reasoning.
Question
Please refer to section 1.3 and 'Programme' in the Glossary of the PRINCE2 Manual. (Note that a collection of related projects being directed to deliver outcomes and benefits related to the organization's strategic objectives would be a programme NOT a project)
Options
- AA temporary team that is created to direct and oversee a collection of related projects in order to
- BA temporary organization that is created for the purpose of delivering one or more business
- CA permanent organization that is created for the purpose of realizing one or more business
- DA permanent team that is created to deliver a series of business change initiatives
How the community answered
(55 responses)- A7% (4)
- B71% (39)
- C18% (10)
- D4% (2)