PR2F · Question #485
Which level of management in the project management team has the ability to review progress and decide whether to continue, change or stop the project?
The correct answer is B. Project Board. See the full explanation below for the reasoning.
Question
Which level of management in the project management team has the ability to review progress and decide whether to continue, change or stop the project?
Options
- AProject Manager
- BProject Board
- CTeam Manager
- DCorporate or programme management
How the community answered
(26 responses)- A4% (1)
- B85% (22)
- C4% (1)
- D8% (2)