What type of progress control is a Checkpoint Report?

The correct answer is C. Time-driven. See the full explanation below for the reasoning.

Question

What type of progress control is a Checkpoint Report?

Options

  • AEvent-driven
  • BException-based
  • CTime-driven
  • DAd hoc-based

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    75% (15)
  • D
    15% (3)