nerdexam
EXIN

PR2F · Question #481

The creation of an Exception Plan often follows which of the following situations?

The correct answer is B. An Exception Report being submitted to the Project Board in the case of a management stage. See the full explanation below for the reasoning.

Question

The creation of an Exception Plan often follows which of the following situations?

Options

  • AA time or cost slippage occurring during a management stage
  • BAn Exception Report being submitted to the Project Board in the case of a management stage
  • CA Stage Plan updated due to an urgent corrective action being taken by the Project Manager
  • DA newly identified risk being captured and documented in the Risk Register

How the community answered

(47 responses)
  • A
    15% (7)
  • B
    79% (37)
  • C
    4% (2)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice