Question
The creation of an Exception Plan often follows which of the following situations?
Options
- AA time or cost slippage occurring during a management stage
- BAn Exception Report being submitted to the Project Board in the case of a management stage
- CA Stage Plan updated due to an urgent corrective action being taken by the Project Manager
- DA newly identified risk being captured and documented in the Risk Register