PR2F · Question #480
Which of the following are factors that need to be taken into consideration when identifying management stages? 1. Where the key decisions points need to be 2. The amount of risk within the project…
The correct answer is B. 1,2,4. See the full explanation below for the reasoning.
Question
Which of the following are factors that need to be taken into consideration when identifying management stages? 1. Where the key decisions points need to be 2. The amount of risk within the project 3. The number of technical stages 4. How confident the Project Board and Project Manager are with proceeding
Options
- A1,2,3
- B1,2,4
- C1,3,4
- D2,3,4
How the community answered
(56 responses)- A5% (3)
- B82% (46)
- C2% (1)
- D11% (6)