PR2F · Question #483
Which of the following is NOT within the authority of the Project Board?
The correct answer is D. Set project-level tolerance. See the full explanation below for the reasoning.
Question
Which of the following is NOT within the authority of the Project Board?
Options
- AApprove the End Project Report
- BSet Stage-level tolerance
- CApprove Stage Plans
- DSet project-level tolerance
How the community answered
(53 responses)- A11% (6)
- B4% (2)
- C6% (3)
- D79% (42)