The correct answer is A. Understand how and when the project's products will be delivered and at what cost. See the full explanation below for the reasoning.
Question
Which is an aim of the Starting up a Project process?
Options
- AUnderstand how and when the project's products will be delivered and at what cost
- BEnsure that there is authority to deliver the project's products
- CDo the minimum necessary in order to decide whether it is worthwhile to even initiate the project
- DCreate the set of management products required to control the project