Which of the following is funded from a change budget?

The correct answer is B. Request for change. See the full explanation below for the reasoning.

Question

Which of the following is funded from a change budget?

Options

  • AFallback plan
  • BRequest for change
  • CAction to reduce a threat
  • DChange Authority

How the community answered

(55 responses)
  • A
    4% (2)
  • B
    73% (40)
  • C
    5% (3)
  • D
    18% (10)