PR2F · Question #446

Which is NOT a factor to consider when defining management stages?

The correct answer is B. When Team Managers are available. See the full explanation below for the reasoning.

Question

Which is NOT a factor to consider when defining management stages?

Options

  • AHow long the project is
  • BWhen Team Managers are available
  • CWhen key decisions are required on the project
  • DThe amount of risk within the project

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    79% (19)
  • C
    4% (1)
  • D
    13% (3)