Which of the following is FALSE?

The correct answer is A. Manage risks is a PRINCE2 principle. See the full explanation below for the reasoning.

Question

Which of the following is FALSE?

Options

  • AManage risks is a PRINCE2 principle
  • BManage by exception is a PRINCE2 principle
  • CFocus on products is a PRINCE2 principle
  • DTailor to suit the project environment is a PRINCE2 principle

How the community answered

(26 responses)
  • A
    73% (19)
  • B
    8% (2)
  • C
    15% (4)
  • D
    4% (1)