According to PRINCE2, which of the following are the aspects of project performance to be managed?

The correct answer is D. Time, cost, quality, scope, benefits, risk. See the full explanation below for the reasoning.

Question

According to PRINCE2, which of the following are the aspects of project performance to be managed?

Options

  • AProcesses, themes, principles
  • BTime, cost, quality, people
  • CTime, cost, quality
  • DTime, cost, quality, scope, benefits, risk

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    3% (1)
  • D
    83% (24)