According to PRINCE2, which of the following is a characteristic of a project compared to that of business operations?

The correct answer is B. Introduces business change. See the full explanation below for the reasoning.

Question

According to PRINCE2, which of the following is a characteristic of a project compared to that of business operations?

Options

  • AIncurs cost
  • BIntroduces business change
  • CDelivers benefits
  • DCreates products

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    82% (27)
  • C
    6% (2)
  • D
    9% (3)