When is the Stage Plan for project initiation produced?

The correct answer is B. Before the Project Board authorize the initiation of the project. See the full explanation below for the reasoning.

Question

When is the Stage Plan for project initiation produced?

Options

  • AImmediately prior to the authority to deliver a project has been given
  • BBefore the Project Board authorize the initiation of the project
  • CAfter the Project Plan has been produced
  • DDuring Managing a Stage Boundary process

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    68% (15)
  • C
    9% (2)
  • D
    18% (4)