PR2F · Question #373
Which is NOT established as part of the Starting Up a Project process?
The correct answer is D. A plan for how and when a measurement of the achievement of the project's benefits can be. See the full explanation below for the reasoning.
Question
Which is NOT established as part of the Starting Up a Project process?
Options
- AA Plan for the work of initiation
- BInformation on the various ways the project can be delivered
- CA description of what the project is to deliver
- DA plan for how and when a measurement of the achievement of the project's benefits can be
How the community answered
(46 responses)- A4% (2)
- B15% (7)
- C9% (4)
- D72% (33)