Which is a specific objective of the Starting Up a Project process?
Options
- ATo establish how the project's products will be delivered and at what cost
- BEnsure there is a common understanding of the benefits expected from the project
- CTo ensure there is business justification for initiating the project?
- DTo approve the Plan for the next Stage