The correct answer is C. Managing, monitoring and controlling of all aspects of an assigned risk. See the full explanation below for the reasoning.
Question
Which statement best describes the responsibilities of a risk actionee?
Options
- AIdentifying risks to the project that might occur in their department
- BOwning and authorizing the use of the risk budget to fund risk responses
- CManaging, monitoring and controlling of all aspects of an assigned risk
- DCarrying out a risk response action to respond to a particular risk