What is the goal of the 'identify context' step as part of the risk management procedure?

The correct answer is B. Gather information about the project environment and objectives. See the full explanation below for the reasoning.

Question

What is the goal of the 'identify context' step as part of the risk management procedure?

Options

  • AIdentify responses to risks identified in the Business Case
  • BGather information about the project environment and objectives
  • CGather information about risks for inclusion in Highlight Reports to the Project Board
  • DIdentify the threats and opportunities that may affect the project's objectives

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    83% (29)
  • C
    6% (2)
  • D
    3% (1)